5
Jul

Northland Power had submitted their REA, Renewable Energy Application for the McLeans Mountain
Project around May 13/10. The REA application was returned about June 14/10 as the application
does not have a enough info and it was deemed incomplete. The REA must include all documents in
table 1 of the REA and all requirements of a class 4 wind farm project. A detailed list has
been provided to Northland Power to complete.Their project does have a comencement date
requirement under their contract with OPA but the REA can continue for 3 -5 years.

Raymond Beaudry
mcsea.ca

Share
Category : Uncategorized